About Work
Day 1 (25 Feb 10 - Day Shift)
On Annual Leave
No replacement required
Day 2 (26 Feb 10 - Day Shift)
Capping Day
Completed the folowing tasks for Parts Prep
- Autoclave
- Cleaning Load - Inprogress
- Parts Washer
- Post Cleaning (OQ) Load 5, 6, 7 & 8 - Completed, placed in Steriset
- Trays Washer
- General Notes
- Please do Chamber Cleaning for Tray Washer follow by LKT & Post Batch Activities
- I&P
- Stop OPN
- LNC - Done
- Follow up with CLN
- Batchsheet will be follow up by Team B tomorrow.
Day 3 (27 Feb 10 - Day Shift)
Took 1/2 day with Elizabeth, Cindy & Faiz
No tasks completed for Parts Prep today as the ultility (Steam, WFI & PFW) is down for maintenance.
Thanks Faiz for sending me home.